On 23 September 2026, the Italian Senate gave final approval to the enabling law on sustainable nuclear energy (Atto Senato n. 1924), following approval by the Chamber of Deputies on 4 June 2026. The law creates the legal basis for Italy’s potential return to nuclear generation, almost four decades after the 1987 referendum led to the closure of its reactors, and delegates the detailed rules to government decrees. The bill’s record is available on the Senate website.
|
The law does |
The law does not |
|
Establish a national framework for sustainable nuclear energy and delegate detailed rules to the government |
Authorise any specific reactor, site or project |
|
Set a 12-month deadline from entry into force for implementing decrees, according to the government and parliamentary reporting |
Set a binding commissioning date for new capacity |
|
Define the scope of the decrees: construction and operation of plants, safety, fuel, radioactive waste, institutional responsibilities, hydrogen production from nuclear energy |
Immediately authorise construction or operation of a particular nuclear facility |
|
Focus on new technologies: small modular reactors, advanced modular reactors, microreactors, fusion |
Select a particular reactor technology or commercial design |
|
Assign a role to the national nuclear safety inspectorate in validating technical certifications |
Create an immediately operational support scheme or generation tariff. Any future financial-support mechanism would require further rules and, where applicable, compliance with EU requirements |
An enabling law (legge delega) sets objectives and principles and delegates the drafting of detailed rules to the government, which adopts them as legislative decrees within a fixed period. The law was published in the Gazzetta Ufficiale on 30 September 2026 and enters into force on 15 October 2026. The government then has 12 months to adopt one or more legislative decrees. The decrees are adopted following the procedural steps prescribed by the law, including the required institutional and parliamentary opinions.
Investment decisions, site selection and construction permits depend on the decrees and on subsequent authorisations. Until then, the law changes the legal framework, not physical supply.
Italy closed its last reactors after the 1987 referendum and rejected a return in a second referendum in 2011. The government frames the new framework around energy security, decarbonisation and the electricity demand expected from electrification, data centres and industry. Italy imports electricity through its interconnections with neighbouring markets, including countries with nuclear generation. Gas-fired generation continues to play an important role in Italian wholesale price formation.
The government has pointed to the 2033–2035 period as an indicative target for first new facilities. The pace will depend on technology licensing, the availability of commercial SMR designs and public acceptance. In this decade, storage and renewables remain the main source of new capacity in Italy.
|
Date |
Milestone |
|
4 June 2026 |
Chamber of Deputies approves the bill (Atto Camera n. 2669) |
|
23 September 2026 |
Senate gives final approval (Atto Senato n. 1924) |
|
29 September 2026 |
Law No. 169 adopted |
|
30 September 2026 |
Law published in Gazzetta Ufficiale No. 227 |
|
15 October 2026 |
Law enters into force |
|
Within 12 months of entry into force |
Government adopts implementing decrees |
|
2033–2035, indicative |
Government objective for the possible launch of the first new facilities; no binding commissioning date has been set |
No. The law creates a legal framework and delegates the detailed rules to the government. Specific projects will require implementing decrees and subsequent authorisations.
Small modular reactors, advanced modular reactors, microreactors and nuclear fusion.
No binding commissioning date has been set. Public statements have referred to the 2033–2035 period as an indicative objective, but delivery will depend on the implementing framework, technology readiness, licensing, site selection and project-specific authorisations.
No. The enabling law does not add generation capacity or directly change current electricity-price formation. Any material market effect would depend on future projects becoming operational.
D.TRADING trades power and gas on the Italian market and across its interconnections with Central and South-Eastern Europe.
D.TRADING is a B2B energy and commodity trading company operating across Central, Eastern, and South-Eastern Europe, including Ukraine, with hubs in Baar (Switzerland), Zagreb (Croatia), Amsterdam (Netherlands), and Kyiv (Ukraine). The company operates in 26 countries.
The company trades power, gas, LNG, and fuels for enterprise and wholesale counterparties, with services that include structured trading, renewable offtake, battery storage route-to-market, and guarantees of origin. In 2025, it traded 12.1 TWh of power and 7.0 TWh of natural gas for more than 130 clients.
This article is prepared by D.TRADING for general informational purposes only and does not constitute legal, financial, investment, accounting, tax, or regulatory advice. The information contained herein is based on publicly available sources and reflects opinion on the regulatory environment as of the publication date. D.TRADING makes no representations or warranties, express or implied, as to the accuracy, completeness, or timeliness of the information provided. This document is not an offer or solicitation to buy or sell any energy products, commodities, or financial instruments.